AEMO has published its connections scorecard for the National Electricity Market (NEM), tracking the progress of generation and storage project applications to reaching full output in the NEM.
The scorecard is produced through AEMOโs work with market participants, as well as transmission and distribution network service providers (NSP) involved in the comprehensive connection process.
Related article: AEMO says renewables โthe most efficient pathโ to net zero
AEMO onboarding and connections group manager Margarida Pimentel said, โCompared to the previous 12 months, the capacity of projects working through the connection process have surged from 30GW to 43GW.โ
โEarly-stage application approvals involving the NSP and AEMO have increased 74%, from 6.9GW to 12GW, and the typical duration reduced by one month, from 10.9 to 9.7 months.
โAEMO has helped reduce the time taken for application approvals through collaborating, specifically by addressing key design elements early in the process and using opportunities to split scope between the NSP and AEMO to reduce duplication of work,โ she said.
Over the past 12 months, projects that have application approvals from their NSP and AEMO are taking longer in the โproponent implementationโ stage, the stage when contracts are established, and plant is constructed.
In FY24, 75% of projects completed this stage within 21 months, compared with 12 months in FY23. The volume of projects currently in this stage has been steadily increasing and is currently sitting at 15GW compared to 11GW a year ago.
These delays can be attributed to issues such as longer equipment lead times, refinancing, delayed contract execution and construction due to the limited resources available across a growing pool of projects, and changeovers in original equipment manufacturers.
โWhile both registration and commissioning has not changed significantly compared to last year, we are starting to see a steady increase in new package submissions for registration, close to 7GW compared to 1.5GW at the same time last year,โ Pimentel said.
โOn a positive note, there has been a significant decrease in the time projects are taking to progress through commissioning, with 75% of projects commissioned to full output within 6.9 months, compared to more than 11 months in June FY23.
Related article: AEMOโs grid forecast update warns of โenergy gapsโ
โContributing to this is a new approach to commissioning AEMO is using with a number of projects, taking learnings from the Federal Governmentโs summer readiness program and industry-supported Connections Reform Initiative trials, which has helped reduce time taken for plant to reach full output,โ she said.
During the month of June 24, four projects totalling 0.72GW received application approval, with the majority from battery projects (365MW), followed by wind (276MW) and solar plus battery (80MW).